Oracle Primavera - PM6 Member for 20 years 6 months Member for 20 years 6 months Submitted by Santosh Bhat on Mon, 2019-12-16 03:38 Permalink Mike,1) Open the project you Mike, 1) Open the project you want to change. 2) Select FILE>EXPORT 3) Select Spreadsheet XLSX as the export option 4) Select the Resource Assignments optoo 5) Ensure the chosen project is ticked 6) Select a Template, or add/modify and esnure this new template includes the data field you want exported (ie Budgeted units) 7) Select a directory and filename for the exported XLSX file and press Finish 8) Now you will have a list of all resource assignments and budgeted units. Modify this spreadsheet file as required, save and close. Now back in P6, 9) select FILE>IMPORT 10) select Spreadsheet XLSX 11) Point to the file you saved in 8) 12) Select the project to import to and press finish. Log in or register to post comments
Member for 20 years 6 months Member for 20 years 6 months Submitted by Santosh Bhat on Mon, 2019-12-16 03:38 Permalink Mike,1) Open the project you Mike, 1) Open the project you want to change. 2) Select FILE>EXPORT 3) Select Spreadsheet XLSX as the export option 4) Select the Resource Assignments optoo 5) Ensure the chosen project is ticked 6) Select a Template, or add/modify and esnure this new template includes the data field you want exported (ie Budgeted units) 7) Select a directory and filename for the exported XLSX file and press Finish 8) Now you will have a list of all resource assignments and budgeted units. Modify this spreadsheet file as required, save and close. Now back in P6, 9) select FILE>IMPORT 10) select Spreadsheet XLSX 11) Point to the file you saved in 8) 12) Select the project to import to and press finish.
Member for
20 years 6 monthsMike,1) Open the project you
Mike,
1) Open the project you want to change.
2) Select FILE>EXPORT
3) Select Spreadsheet XLSX as the export option
4) Select the Resource Assignments optoo
5) Ensure the chosen project is ticked
6) Select a Template, or add/modify and esnure this new template includes the data field you want exported (ie Budgeted units)
7) Select a directory and filename for the exported XLSX file and press Finish
8) Now you will have a list of all resource assignments and budgeted units. Modify this spreadsheet file as required, save and close.
Now back in P6,
9) select FILE>IMPORT
10) select Spreadsheet XLSX
11) Point to the file you saved in 8)
12) Select the project to import to and press finish.