Microsoft Project Member for 6 years 4 months Member for 6 years 4 months Submitted by saikrishna raju on Thu, 2019-12-12 05:39 Permalink How to assign the Work How to assign the Work Resources,Because in that it is Asking Per day cost,the Cost is already loaded in the Schedule. can you Please send me one Example how to Load the Labour quantity in Schedule. Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2019-12-11 17:59 Permalink Hello,Insert the filed "Work" Hello, Insert the filed "Work" in the table you are working it, and enter the labor quantity for each tack; if you do not assigne Work resources to the tasks, MS Project will not calculate the task duration from the labor quantity. Alexandre Log in or register to post comments
Member for 6 years 4 months Member for 6 years 4 months Submitted by saikrishna raju on Thu, 2019-12-12 05:39 Permalink How to assign the Work How to assign the Work Resources,Because in that it is Asking Per day cost,the Cost is already loaded in the Schedule. can you Please send me one Example how to Load the Labour quantity in Schedule.
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2019-12-11 17:59 Permalink Hello,Insert the filed "Work" Hello, Insert the filed "Work" in the table you are working it, and enter the labor quantity for each tack; if you do not assigne Work resources to the tasks, MS Project will not calculate the task duration from the labor quantity. Alexandre
Member for
6 years 4 monthsHow to assign the Work
How to assign the Work Resources,Because in that it is Asking Per day cost,the Cost is already loaded in the Schedule.
can you Please send me one Example how to Load the Labour quantity in Schedule.
Member for
22 years 9 monthsHello,Insert the filed "Work"
Hello,
Insert the filed "Work" in the table you are working it, and enter the labor quantity for each tack;
if you do not assigne Work resources to the tasks, MS Project will not calculate the task duration from the labor quantity.
Alexandre