I do noticed the same issue with some of my Projects. But practically, Actual Unit and Actual Cost must be recorded manually.
You can work around, export the Resource assignment to excel then the actual units equals multiplying the Budgeted Units by the Performance % of the activity. Import back the Resource assigment then you get the actual units and as well the Actual Cost.
Member for
16 years 3 monthsGo to Projects make sure you
Go to Projects make sure you project is open click on the Calculations tab on the right under Resource Assignments
make aure that When updating Actual Units or Costs that
Subtract Actual from At Completion is checked and that
Recalculate Actual Units and Costs when duration % complete changes is checked
also make sure that Link Actual and Actual This Period Units and Cost is checked.
Member for
15 years 11 monthsHi,I do noticed the same
Hi,
I do noticed the same issue with some of my Projects. But practically, Actual Unit and Actual Cost must be recorded manually.
You can work around, export the Resource assignment to excel then the actual units equals multiplying the Budgeted Units by the Performance % of the activity. Import back the Resource assigment then you get the actual units and as well the Actual Cost.
Regards,