Resource Assignment on Activity Completed or in Progress

Member for

16 years 3 months

Go to Projects make sure you project is open click on  the Calculations tab on the right under Resource Assignments 

make aure that When updating Actual Units or Costs that 

Subtract Actual from At Completion is checked and that 

Recalculate Actual Units and Costs when duration % complete changes is checked

also make sure that Link Actual and Actual This Period Units and Cost is checked.

Member for

15 years 11 months

Hi,

I do noticed the same issue with some of my Projects. But practically, Actual Unit and Actual Cost must be recorded manually.

You can work around, export the Resource assignment to excel then the actual units equals multiplying the Budgeted Units by the Performance % of the activity. Import back the Resource assigment then you get the actual units and as well the Actual Cost.

 

Regards,