P6 - resource is not showing activities that are completed

Member for

16 years 3 months

go to view resource usage profile and make sure that on the dat tab that you have the actua box checked. 

Member for

21 years

The P6 stacked histogram shows "At Completion" hours/costs - so stage 1 of your investigation is to show that value besiide the "Budgeted" numbers you have highlighted.......

Yes, "At Completion" is a bit bonkers....