Duration In Days

Member for

6 years 2 months

Hi,

You said "i am in 5 th day of my project and i realized that i need 2 days more to finish this task".

Is it 2 more days in addition to the 5th day (when you realized that) or 2 more days in additon to the 10 days?

Member for

14 years 8 months

it is called (Late Finish Date) on the Column Tab