Percent Complete Changed when Baseline is inserted

Member for

16 years 3 months

just ask here or in linkedin and we will set you strainght.

Member for

15 years 9 months

Hello Zoltan

Thanks for this information. I recently moved to a new P6 database and forgot to change this default setting. Cost me hours to correct. Paul Harris also published this particular setting in the Admin.

Regards Johannes

Member for

16 years 3 months

goto 

Admin

Admin Preferences

Earned Value Tab

Then at the bottom under earned Value Calculations

make sure that the selection is Budgeted Values with current dates NOT PLANNED DATES