if i do not change the time period to 10 hrs/day (keeping 8hrs/day), what could be the changes in my schedule, while importing a programme developed with the time period settings of 10 hrs/day.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Thu, 2019-07-25 14:27
there is no such thing as a fixed duration & units with the settings as 8 hrs/day. The duration type is just a type the hours per day depens on your calendar being used i.e 10 hours per day, and the resources Default Units/Time and the Hours per time period set up in the Users Preferences.
change your setting to 10 hours per day under
under Admin preferences the Time Period tab make sure that Allow users to specify the number of work hours for each time period is checked.
then go to Edit Users Preferences
Time units tab and chaneg the Hours per time period to 10 hours/day 50 hours/week 215 Hours/month 2500 Hours/Year
Zoltan, If I am using fixed duration & units with the settings as 8 hrs/day. While importing the 10hrs/day schedule, how it will be reflected, what changes may happen.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Tue, 2019-07-23 14:03
Kannan your scenerio depends on duation type if you are using fixed duration and units/time then the duration will NOT change hence the term Fixed Duration.
In the Common database, Under Admin Preferences, is the option "Use assigned Calendar to specifiy the number of work hours for each time period" ticked, or unticked?
Member for
17 years 4 monthsif i do not change the time
if i do not change the time period to 10 hrs/day (keeping 8hrs/day), what could be the changes in my schedule, while importing a programme developed with the time period settings of 10 hrs/day.
Member for
16 years 3 monthsthere is no such thing as a
there is no such thing as a fixed duration & units with the settings as 8 hrs/day. The duration type is just a type the hours per day depens on your calendar being used i.e 10 hours per day, and the resources Default Units/Time and the Hours per time period set up in the Users Preferences.
change your setting to 10 hours per day under
under Admin preferences the Time Period tab make sure that Allow users to specify the number of work hours for each time period is checked.
then go to Edit Users Preferences
Time units tab and chaneg the Hours per time period to 10 hours/day 50 hours/week 215 Hours/month 2500 Hours/Year
Member for
17 years 4 monthsZoltan, If I am using fixed
Zoltan, If I am using fixed duration & units with the settings as 8 hrs/day. While importing the 10hrs/day schedule, how it will be reflected, what changes may happen.
Member for
16 years 3 monthsKannan your scenerio depends
Kannan your scenerio depends on duation type if you are using fixed duration and units/time then the duration will NOT change hence the term Fixed Duration.
Member for
17 years 4 monthsIn the sub contractor's admin
In the sub contractor's admin settings it will be 10 hrs per day. For 5 days duration it will be 50 hrs.
In your admin settings it is 8 hrs per day. So when you import the 50 hrs, it will be recalulated as 50/8= 6.25 days.
Change the settings in the admin preferences.
Best Regards
Kannan
Member for
16 years 3 monthsunder Admin preferences the
under Admin preferences the Time Period tab make sure that Allow users to specify the number of work hours for each time period is checked.
it looks like what you have listed are conflicting you are working 10 hours per day but your preferences are set or 8 hours per day.
Member for
20 years 6 monthsIn the Common database, Under
In the Common database, Under Admin Preferences, is the option "Use assigned Calendar to specifiy the number of work hours for each time period" ticked, or unticked?