Oracle Primavera - PM6 Member for 20 years 6 months Member for 20 years 6 months Submitted by Santosh Bhat on Mon, 2019-07-08 14:38 Permalink As well as viewing the As well as viewing the Original Duration column, also include the following: Original Duration (OD) Actual Duration (AD) Remaining Duration (RD) At Completion Duration (ACD) This will help to explain how the various duration values are used. As a rule AD+RD will always equal ACD OD = RD when the activity has not started AD = ACD when the activity has finished Note that none of the above refer to durations from any baseline projects. For that you need to Look at BL/BL1/BL2 Duration values as well. Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2019-07-08 13:38 Permalink if you dont want it to do if you dont want it to do that then remove it. What the expected finsh date will do will automatically calculate the duration from the date that the activity is schedule to start to the expected finish date that you entered. Member for 21 years Member for 21 years Submitted by David Kelly on Mon, 2019-07-08 10:17 Permalink If your activity has not If your activity has not started, That is what it is supposed to do. Log in or register to post comments
Member for 20 years 6 months Member for 20 years 6 months Submitted by Santosh Bhat on Mon, 2019-07-08 14:38 Permalink As well as viewing the As well as viewing the Original Duration column, also include the following: Original Duration (OD) Actual Duration (AD) Remaining Duration (RD) At Completion Duration (ACD) This will help to explain how the various duration values are used. As a rule AD+RD will always equal ACD OD = RD when the activity has not started AD = ACD when the activity has finished Note that none of the above refer to durations from any baseline projects. For that you need to Look at BL/BL1/BL2 Duration values as well.
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2019-07-08 13:38 Permalink if you dont want it to do if you dont want it to do that then remove it. What the expected finsh date will do will automatically calculate the duration from the date that the activity is schedule to start to the expected finish date that you entered.
Member for 21 years Member for 21 years Submitted by David Kelly on Mon, 2019-07-08 10:17 Permalink If your activity has not If your activity has not started, That is what it is supposed to do.
Member for
20 years 6 monthsAs well as viewing the
As well as viewing the Original Duration column, also include the following:
This will help to explain how the various duration values are used. As a rule
Note that none of the above refer to durations from any baseline projects. For that you need to Look at BL/BL1/BL2 Duration values as well.
Member for
16 years 3 monthsif you dont want it to do
if you dont want it to do that then remove it.
What the expected finsh date will do will automatically calculate the duration from the date that the activity is schedule to start to the expected finish date that you entered.
Member for
21 yearsIf your activity has not
If your activity has not started, That is what it is supposed to do.