Budgeted resources changes everytime i import data

Member for

21 years 1 month

Hi Rolyn Transfer Autocost Rule from another Project. (One you are sure that you did not have any problems with)



Also have a look as to earned Value are you using Target Project or Current Project

Member for

21 years 5 months

Alex,

the budgeted quantity of some of my activities changes, some have increased and some decreases... there’s no pattern whatsoever. therefore my budgeted cost also changes. This is the first time I’ve encountered such problem like this. and this problem only occurs every time I import data (i.e. AS, AF & PCT).

Member for

24 years 6 months

Rolyn,



I would check your autocost rules (Tools, Optiosn, Autocost).



You mentioned it is cost loaded and you collect AS, AF and PCT. To have the system estimate the actual you will need to have the option checked to Use updated percentage against budget to estimate actual cost (or quantity) to date.



If these are not set and you are not collecting and inputting/importing the actual cost (or quantity) then as you import the AF the RD becomes 0 and forces the CTC and CAC (and QTC/QAC) to zero and you appear to lose those values from the Project.



HTH

Member for

22 years 8 months

Can you please describe a bit more



is your quantity or $ changed

is increase or decrease

how you update your actuals (Import and Export)



cheers



Alex