Linking activities between P3 files

Member for

24 years 6 months

Further to Dattatreya’s response be aware that if you link back and forth between multiple Project Groups you may have to schedule the Project Groups many times in the correct sequence to get the correct finish date for all Project Groups. I would strongly encourage you to merge them into the one Project Group to avoid this issue (you can then schedule the Project Group with the appropriate data date option set).



The only valid use I have had for Interproject relationships is where the planning unit is different. eg building project over exiting electrified rail line with building project planned in days and track possessions in hours (for track upgrades or working above high voltage lines prior to enclosure). All relationships go one way from the daily building project to the hourly possession works schedule.

Member for

22 years 6 months

Open the interproject , give the password "INTRPROJ"

It opens Interproject Relation ship manager.

Go to--> new; Add Project group/s.

Define relationships between activities of different projects as you desire as well as imposed dates.

Save the file ; Open the Predecessor project (be sure you have recognise interproject relationships checked in the schedule options)

Schedule & then schedule the successor projects.

Hope this works for you.



Regards

Dattatreya