Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2019-03-18 13:42 Permalink are you updating remaining are you updating remaining duration ? what calculation are you using for earned value ? this is under Admin Preferences then the Earned Value Tab. Technique for computing Estimate to Compete (ETC) and at the bottom Earned value calculation should be Earned value with current dates Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2019-03-18 13:42 Permalink are you updating remaining are you updating remaining duration ? what calculation are you using for earned value ? this is under Admin Preferences then the Earned Value Tab. Technique for computing Estimate to Compete (ETC) and at the bottom Earned value calculation should be Earned value with current dates
Member for
16 years 3 monthsare you updating remaining
are you updating remaining duration ?
what calculation are you using for earned value ?
this is under
Admin Preferences
then the Earned Value Tab.
Technique for computing Estimate to Compete (ETC)
and at the bottom Earned value calculation should be Earned value with current dates