Budgeted Costs

Member for

22 years 8 months

The only think I know to remove non labor budget is reverse status for Actual Finihsed activity.



R U sure it is associated with Start date??

Member for

20 years 10 months

I cannot think of a scenario that would reset the task’s budget to zero by simply statusing the task with an actual start date.



Here is a place to start.



1. Go to the Project’s Screen , select your project in question , and then go to the Calculations tab (located at the bottom of the screen). This tab contains settings that impact activity and assignment calculations. Perhaps you will notice a setting here that is not configured the way you would like.







Regards,

Bill