I cannot think of a scenario that would reset the tasks budget to zero by simply statusing the task with an actual start date.
Here is a place to start.
1. Go to the Projects Screen , select your project in question , and then go to the Calculations tab (located at the bottom of the screen). This tab contains settings that impact activity and assignment calculations. Perhaps you will notice a setting here that is not configured the way you would like.
Member for
22 years 8 monthsRE: Budgeted Costs
The only think I know to remove non labor budget is reverse status for Actual Finihsed activity.
R U sure it is associated with Start date??
Member for
20 years 10 monthsRE: Budgeted Costs
I cannot think of a scenario that would reset the tasks budget to zero by simply statusing the task with an actual start date.
Here is a place to start.
1. Go to the Projects Screen , select your project in question , and then go to the Calculations tab (located at the bottom of the screen). This tab contains settings that impact activity and assignment calculations. Perhaps you will notice a setting here that is not configured the way you would like.
Regards,
Bill