Very good post. What happens if the activities have already those resources assigned? Ticking the option 'calculate cost from units' at the resource level does not update the same field for all activities where that resource is already assigned.
The clumsy solution is to go at each activity and tick the field which might take some time if you have thousands of activities or do a global change and modify that field from 'no' to 'yes'.
Actuals should come from your actual projects costs (timesheets, POs, Invoices, etc). It would be easy if your programme activities are mirrored with BOQ items and your QS/Cost Controllers are very cooperative in sharing this info. An excel sheet can be utilize for updating and exporting/importing to/from P6.
Since when you imoprt again to another computer the Unit /Price will be 0 and all manuall cost u add it it will become zero ,
but you can apply global change ,by taking all the cost to custmized coloum by using global change ,and after import you need to apply global change again to get the value in your cost .
Just a followup question regarding this thread, if i manually input the budgeted cost and actual cost (having no price/unit) and run the program. I'm having what I need. But upon exporting the XER file to another computer, all the Costs became zero. Is that an implication due to manually inputing of costs?
I'm having the same problem but in the opposite manner. Among the resources I have assigned, some has the option "Auto compute actuals" checked and the others does not. However, when I update the schedule, I am getting actual costs for both checked & unchecked resources as I expect to see "0" for unchecked resources.
Thanks in advance.
Member for
18 years 9 months
Member for18 years10 months
Submitted by Haitham Khaireldin on Mon, 2011-05-09 04:56
Can you please re-upload the pictures as i am not able to see them.
Actually i am facing the same problem. I have budgeted cost without unit rates thats why i am only using the auto compute actuals option but after updating schedule the actual cost is not updated accordingly..
Am i missing something??!!
I think your problem is down to the way your resource dictionary is configured (depending upon your set up, may need system administrator to sort out - you will at least need admin rights to configure).
If your resource doesn't have the 'auto compute actuals' box checked in the dictionary, it will not be possible to calculate actual costs from the number of units progressed.
I have enclosed a couple of screen shots which hopefully explains what is happening.
[[wysiwyg_imageupload:191:height=360,width=507]]
Each resource has 2 calculation settings embedded with the resource. Auto Compute Actuals and Calculate Costs from Units. Auto Compute Actuals does exactly what it says; P6 will calculate the actual price based upon the number of units used. The second tick box is Calculate Costs from Units. This will calculate the Budgeted Total Cost for the resource assignment based upon the resource unit price and the number of units assigned (note, if this is selected with a zero unit price, each time you reschedule, the BTC for the resource will default to zero even if you have manually input a price).
[[wysiwyg_imageupload:193:height=198,width=538]]
The second screen above now shows 2 activities. Both are for the same duration but one has the resource assigned with both ‘Calculate Costs from Units’ and ‘Auto Compute Actuals’ selected.
For the purpose of this demonstration I have created 2 resources, one with a unit cost and the other without.
The project has been scheduled to the latest data date.
[[wysiwyg_imageupload:185:height=260,width=535]]
The screen shot above shows the starting point with the new resources assigned.
Now, for arguments sake, I have manually assigned a budget to the resource with the zero unit cost.
The next screen shot shows what happens when progress is assigned. For this example, I have used the update progress tool.
Note activity A1000 has calculated the actual cost based upon the number of units burned in the progress update. The other activity A1010 has not assigned any actual cost.
[[wysiwyg_imageupload:186:height=275,width=532]]For the next example (below), I have manually assigned a budgeted total cost of $10,000.
[[wysiwyg_imageupload:187:height=278,width=537]]
I will also have to manually assign the actual cost as well (see below).
[[wysiwyg_imageupload:188:height=274,width=533]]
For the final part of the demonstration, I am going to check the ‘Calculate Costs from Units’ box for activity A1010. Remember, this activity has a zero unit cost.
The following warning will appear.
[[wysiwyg_imageupload:189:]]
[[wysiwyg_imageupload:190:height=281,width=511]]
Note now the budget which I manually assigned to be $10k has reset to zero as the resource unit price is $0 (80 hours x $0 = $0).
I hope this clears things up?
Cheers
Simon
Member for
14 years 11 months
Member for15 years
Submitted by losin_my_religion on Wed, 2011-01-19 05:44
You have to "check" the option "Auto compute Actuals" against the resource name, where you want the actuals to be updated automatically. You can find it under "details" when you make a new resource or add a column in the resources view.
Member for
16 years 3 monthsbudget costs dates will not
budget costs dates will not change the actual costs and the remaining costs wil change
if you have link actual units and costs to duration % complete. And you update the duration % complete
this is done at the project level make sure that your project is open
Member for
6 years 7 monthsMr. Simon WillsonGood
Mr. Simon Willson
Good Evening!
I cannot see the pictures, can you please share on email?
Member for
6 years 7 monthsMy Program contains only
My Program contains only Material Cost.
I have updated the progress manually, and the program dates have been changed to new dates.
But the dates for Budgeted Units did not change.
Can anyone please help, I have to submitt my project Tomorrow.
Member for
16 years 3 monthsactual costs will not update
actual costs will not update automaticaly unlesss you are using clacualte costs from units.
units will update actuals based on percent complete if you have the link checked.
Member for
11 years 2 monthsHi Simon Willson,Pictures are
Hi Simon Willson,
Member for
14 years 8 monthsHello Simon Willson,I am not
Hello Simon Willson,
I am not able to see these pictures what you uploaded on web site.
Would you send my e-mail please?
alpertunga_2601@hotmail.com
Regards
Member for
14 years 3 monthsVery good post. What happens
Very good post. What happens if the activities have already those resources assigned? Ticking the option 'calculate cost from units' at the resource level does not update the same field for all activities where that resource is already assigned.
The clumsy solution is to go at each activity and tick the field which might take some time if you have thousands of activities or do a global change and modify that field from 'no' to 'yes'.
Member for
20 years 2 monthsDev, Actuals should come from
Dev,
Actuals should come from your actual projects costs (timesheets, POs, Invoices, etc). It would be easy if your programme activities are mirrored with BOQ items and your QS/Cost Controllers are very cooperative in sharing this info. An excel sheet can be utilize for updating and exporting/importing to/from P6.
Kind regards,
R. Catalan
Member for
14 years 1 monthhi Marwin Since when you
hi Marwin
Since when you imoprt again to another computer the Unit /Price will be 0 and all manuall cost u add it it will become zero ,
but you can apply global change ,by taking all the cost to custmized coloum by using global change ,and after import you need to apply global change again to get the value in your cost .
Member for
15 years 11 monthsHi, Just a followup question
Hi,
Just a followup question regarding this thread, if i manually input the budgeted cost and actual cost (having no price/unit) and run the program. I'm having what I need. But upon exporting the XER file to another computer, all the Costs became zero. Is that an implication due to manually inputing of costs?
Member for
14 years 5 monthsI'm having the same problem
I'm having the same problem but in the opposite manner. Among the resources I have assigned, some has the option "Auto compute actuals" checked and the others does not. However, when I update the schedule, I am getting actual costs for both checked & unchecked resources as I expect to see "0" for unchecked resources.
Thanks in advance.
Member for
18 years 9 monthsThe program has a resource
The program has a resource which is "Cost" and the budgeted cost is loaded without unit price. Thats why i have only "Auto Compute Actuals" turned on
Does that mean, I should update the cost manually? then what are the actuals which are auto computed?
I just figured out that when I change the activity % complete, the budgeted/actual/remaining units change but the cost does not change!!!
Member for
16 yearsHaitham,Are you assigning a
Haitham,
Are you assigning a budget manually?
or you're using resources?
If you're using resources.
Go to ----> Enterprise Menu----> Resources
Find your resource in the upper part of the window. Once you find it , click on its name.
In the lower part of the window click the "Details" tab. Turn on both "Auto Compute Actuals" and Calculate "Costs from Units" for this resource.
I think you need to have a Price/Unit under the "Unit & Prices" tab as well.
Once done assign your resource to your activity...etc.
Member for
18 years 9 monthsAnyone?....
Anyone?....
Member for
18 years 9 monthsHi Simon,Can you please
Hi Simon,
Can you please re-upload the pictures as i am not able to see them.
Actually i am facing the same problem. I have budgeted cost without unit rates thats why i am only using the auto compute actuals option but after updating schedule the actual cost is not updated accordingly..
Am i missing something??!!
Please this is very urgent
Member for
18 years 5 monthsHi Simon,It was clear and
Hi Simon,
It was clear and great help to me.
I have changed my settings now and it works.
thanks for the support.
cheers,
Dev
Member for
18 years 11 monthsHi Dev, I think your problem
Hi Dev,
I think your problem is down to the way your resource dictionary is configured (depending upon your set up, may need system administrator to sort out - you will at least need admin rights to configure).
If your resource doesn't have the 'auto compute actuals' box checked in the dictionary, it will not be possible to calculate actual costs from the number of units progressed.
I have enclosed a couple of screen shots which hopefully explains what is happening.
[[wysiwyg_imageupload:191:height=360,width=507]]
Each resource has 2 calculation settings embedded with the resource. Auto Compute Actuals and Calculate Costs from Units. Auto Compute Actuals does exactly what it says; P6 will calculate the actual price based upon the number of units used. The second tick box is Calculate Costs from Units. This will calculate the Budgeted Total Cost for the resource assignment based upon the resource unit price and the number of units assigned (note, if this is selected with a zero unit price, each time you reschedule, the BTC for the resource will default to zero even if you have manually input a price).
[[wysiwyg_imageupload:193:height=198,width=538]]
The second screen above now shows 2 activities. Both are for the same duration but one has the resource assigned with both ‘Calculate Costs from Units’ and ‘Auto Compute Actuals’ selected.
For the purpose of this demonstration I have created 2 resources, one with a unit cost and the other without.
The project has been scheduled to the latest data date.
[[wysiwyg_imageupload:185:height=260,width=535]]
The screen shot above shows the starting point with the new resources assigned.
Now, for arguments sake, I have manually assigned a budget to the resource with the zero unit cost.
The next screen shot shows what happens when progress is assigned. For this example, I have used the update progress tool.
Note activity A1000 has calculated the actual cost based upon the number of units burned in the progress update. The other activity A1010 has not assigned any actual cost.
[[wysiwyg_imageupload:186:height=275,width=532]]For the next example (below), I have manually assigned a budgeted total cost of $10,000.
[[wysiwyg_imageupload:187:height=278,width=537]]
I will also have to manually assign the actual cost as well (see below).
[[wysiwyg_imageupload:188:height=274,width=533]]
For the final part of the demonstration, I am going to check the ‘Calculate Costs from Units’ box for activity A1010. Remember, this activity has a zero unit cost.
The following warning will appear.
[[wysiwyg_imageupload:189:]]
[[wysiwyg_imageupload:190:height=281,width=511]]
Note now the budget which I manually assigned to be $10k has reset to zero as the resource unit price is $0 (80 hours x $0 = $0).
I hope this clears things up?
Cheers
Simon
Member for
14 years 11 monthsHi,You have to "check" the
Hi,
You have to "check" the option "Auto compute Actuals" against the resource name, where you want the actuals to be updated automatically. You can find it under "details" when you make a new resource or add a column in the resources view.
Regards
Amit