Oracle Primavera - PM6 Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2019-02-27 09:58 Permalink Hi Ron,in the preview setup Hi Ron, in the preview setup dialog, go to Options, check that Gantt chart is checked then, fix the Timescale Start and Finish dates, presumably to Project Start and Project Finish have a good day, Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Wed, 2019-02-27 09:58 Permalink Hi Ron,in the preview setup Hi Ron, in the preview setup dialog, go to Options, check that Gantt chart is checked then, fix the Timescale Start and Finish dates, presumably to Project Start and Project Finish have a good day, Alexandre
Member for
22 years 9 monthsHi Ron,in the preview setup
Hi Ron,
in the preview setup dialog, go to Options,
check that Gantt chart is checked
then, fix the Timescale Start and Finish dates, presumably to Project Start and Project Finish
have a good day,