Printing Gantt Chart

Member for

22 years 9 months

Hi Ron,

in the preview setup dialog, go to Options,

check that Gantt chart is checked

then, fix the Timescale Start and Finish dates, presumably to Project Start and Project Finish

have a good day,

Alexandre