Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2019-02-19 13:17 Permalink the only way is can happens the only way is can happens is that 1. there are no predecrssors to the milestones. or 2. all of the predecessors have been completed and the milestones are riding the data date thats it Member for 7 years Member for 7 years Submitted by Saqib Khan on Tue, 2019-02-19 12:23 Permalink Thanks Anoon for your Thanks Anoon for your reply. But i have logically linked all the activities. Still problem is there. :( Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Tue, 2019-02-19 12:12 Permalink First, make sure that your First, make sure that your activities were logically linked before pressing F9. Remember, do not enter dates manually, only durations and then play with your mouse for defining logics. Just practice and later on you will enjoy it! Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2019-02-19 13:17 Permalink the only way is can happens the only way is can happens is that 1. there are no predecrssors to the milestones. or 2. all of the predecessors have been completed and the milestones are riding the data date thats it
Member for 7 years Member for 7 years Submitted by Saqib Khan on Tue, 2019-02-19 12:23 Permalink Thanks Anoon for your Thanks Anoon for your reply. But i have logically linked all the activities. Still problem is there. :(
Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Tue, 2019-02-19 12:12 Permalink First, make sure that your First, make sure that your activities were logically linked before pressing F9. Remember, do not enter dates manually, only durations and then play with your mouse for defining logics. Just practice and later on you will enjoy it!
Member for
16 years 3 monthsthe only way is can happens
the only way is can happens is that
1. there are no predecrssors to the milestones.
or
2. all of the predecessors have been completed and the milestones are riding the data date
thats it
Member for
7 yearsThanks Anoon for your
Thanks Anoon for your reply.
But i have logically linked all the activities. Still problem is there. :(
Member for
19 years 1 monthFirst, make sure that your
First, make sure that your activities were logically linked before pressing F9. Remember, do not enter dates manually, only durations and then play with your mouse for defining logics. Just practice and later on you will enjoy it!