LoE budgeted units not matching activity calendar

Member for

16 years 3 months

if you assign a budget to a LOE activity type you MUST assign a resource CURE or the units will all stuck up on the data date.

Member for

13 years 11 months

Hmm... have just restarted Primavera and all appears to be displaying as expected in the resource spreadsheet. Weird!