Resource Profile Unit of Measure labelling

Member for

13 years 4 months

Thjanks Rafael, it was the Show Unit Label toggle. Much appreciated for the link.

Member for

21 years 8 months

The following link might help.

https://doduykhuong.com/2017/07/31/why-is-unit-of-measure-not-showing-in-resource-usage-profile-in-primavera-p6/

  • Be reminded that it is an average value and not the maximum. The smaller the time interval the closer you will get. 
  • When using partial workloads it might not even get close. 
  • That you use a label such as "Men Required" it does not means it will give you the maximum, it will still give you an average calculated on an arbitrary number.  
  • I suggest using a label that includes the word "Average" to warn others it is not necessarily the maximum required during the time interval.

The following simple scenario combines different calendars and partial workloads you can try yourself.

2019-01-31-Resource-Profile

Good Luck