I think you missunderstood my problem, let me try again
I have a level of effort activity i.e. Project Management and assinged a PM to this activity. Now duration of this activity will span till project completion date.
Now once I assigned resource, this activity should display its total cost to the project. Its cost remains the same which is ZERO, irrespective of its duration. Moreover if project duration inceases this leo activity is not creating any effect to prject cost.
What I think the cost of leo activity should increase if duration increaes, causing the project cost to increae too.
I think you missunderstood my problem, let me try again
I have a level of effort activity i.e. Project Management and assinged a PM to this activity. Now duration of this activity will span till project completion date.
Now once I assigned resource, this activity should display its total cost to the project. Its cost remains the same which is ZERO, irrespective of its duration. Moreover if project duration inceases this leo activity is not creating any effect to prject cost.
What I think the cost of leo activity should increase if duration increaes, causing the project cost to increae too.
I think you missunderstood my problem, let me try again
I have a level of effort activity i.e. Project Management and assinged a PM to this activity. Now duration of this activity will span till project completion date.
Now once I assigned resource, this activity should display its total cost to the project. Its cost remains the same which is ZERO, irrespective of its duration. Moreover if project duration inceases this leo activity is not creating any effect to prject cost.
What I think the cost of leo activity should increase if duration increaes, causing the project cost to increae too.
please help
regards
Mansoor
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Tue, 2019-01-22 13:34
assign a resource and cost to it and also assign a curve. If you do not assign a curve it will stack the resource on the data date. By its definition the loe wil progress as the work does in between the choosen predecessor and successor
Member for
21 years 8 monthsI am not a P6 user but in
I am not a P6 user but in occasions I must deal with schedules submitted in P6 format still I noticed the following.
I hope this can give you some clues in order to fix the bar and the assignments.
This is as far as I can go.
Good luck.
Member for
9 years 10 monthsstill nothere is the
still not
here is the screenshot
[[wysiwyg_imageupload:6461:]]
Member for
16 years 3 monthsimpossible this will add it
impossible this will add it to the total
make sure you have not filtered out loe activites or this particular resource
Member for
9 years 10 monthsHiI think you missunderstood
Hi
I think you missunderstood my problem, let me try again
I have a level of effort activity i.e. Project Management and assinged a PM to this activity. Now duration of this activity will span till project completion date.
Now once I assigned resource, this activity should display its total cost to the project. Its cost remains the same which is ZERO, irrespective of its duration. Moreover if project duration inceases this leo activity is not creating any effect to prject cost.
What I think the cost of leo activity should increase if duration increaes, causing the project cost to increae too.
please help
regards
Mansoor
Member for
9 years 10 monthsHiI think you missunderstood
Hi
I think you missunderstood my problem, let me try again
I have a level of effort activity i.e. Project Management and assinged a PM to this activity. Now duration of this activity will span till project completion date.
Now once I assigned resource, this activity should display its total cost to the project. Its cost remains the same which is ZERO, irrespective of its duration. Moreover if project duration inceases this leo activity is not creating any effect to prject cost.
What I think the cost of leo activity should increase if duration increaes, causing the project cost to increae too.
please help
regards
Mansoor
Member for
9 years 10 monthsHiI think you missunderstood
Hi
I think you missunderstood my problem, let me try again
I have a level of effort activity i.e. Project Management and assinged a PM to this activity. Now duration of this activity will span till project completion date.
Now once I assigned resource, this activity should display its total cost to the project. Its cost remains the same which is ZERO, irrespective of its duration. Moreover if project duration inceases this leo activity is not creating any effect to prject cost.
What I think the cost of leo activity should increase if duration increaes, causing the project cost to increae too.
please help
regards
Mansoor
Member for
16 years 3 monthsassign a resource and cost to
assign a resource and cost to it and also assign a curve. If you do not assign a curve it will stack the resource on the data date. By its definition the loe wil progress as the work does in between the choosen predecessor and successor