Asta Powerproject Member for 7 years Member for 7 years Submitted by AustinR314 on Tue, 2018-10-23 04:31 Permalink Thank you Mike and Andrew. Thank you Mike and Andrew. Those helped me. Regards, Austin Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2018-10-18 14:59 Permalink Hi Austin - Welcome to Hi Austin - Welcome to Planning Planet You can also set week 1 as the works start date by right click the date zone and set the date for weeks 1. Earlir dates will show as minus numbers. Best regards Mike T. Member for 12 years 2 months Member for 12 years 2 months Submitted by andyjwill on Thu, 2018-10-18 12:07 Permalink Hi File-Properties-Advanced Hi File-Properties-Advanced properties -change the imposed start date. Also make sure the date of the project report date is the new date you want Andrew Log in or register to post comments
Member for 7 years Member for 7 years Submitted by AustinR314 on Tue, 2018-10-23 04:31 Permalink Thank you Mike and Andrew. Thank you Mike and Andrew. Those helped me. Regards, Austin
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2018-10-18 14:59 Permalink Hi Austin - Welcome to Hi Austin - Welcome to Planning Planet You can also set week 1 as the works start date by right click the date zone and set the date for weeks 1. Earlir dates will show as minus numbers. Best regards Mike T.
Member for 12 years 2 months Member for 12 years 2 months Submitted by andyjwill on Thu, 2018-10-18 12:07 Permalink Hi File-Properties-Advanced Hi File-Properties-Advanced properties -change the imposed start date. Also make sure the date of the project report date is the new date you want Andrew
Member for
7 yearsThank you Mike and Andrew.
Thank you Mike and Andrew. Those helped me.
Regards,
Austin
Member for
19 years 10 monthsHi Austin - Welcome to
Hi Austin - Welcome to Planning Planet
You can also set week 1 as the works start date by right click the date zone and set the date for weeks 1.
Earlir dates will show as minus numbers.
Best regards
Mike T.
Member for
12 years 2 monthsHi File-Properties-Advanced
Hi
File-Properties-Advanced properties -change the imposed start date.
Also make sure the date of the project report date is the new date you want
Andrew