When we want to link several activities of similar type to define a sequence we need to manually link one by one. like FS if we have an option to choose whatever a relation type to be considered as default by the program, we can complete the task simply. In my housing project we have 80 roads with 9 different utilities where we have to give such relations on a go.
Member for
16 years 3 monthsno why do people always want
no why do people always want to do things backwards ?
Member for
21 years 8 monthsWhy not defining link type
Why not defining link type when performing multiple links as a single step?
You can create a filter to display only selected activities when linking activities on a job with many activities to make it easier.
Maybe you did not looked for the option for performing multiple links as a single step within your software, it is not an uncommon task.
Good luck.
Member for
11 yearsWhen we want to link several
When we want to link several activities of similar type to define a sequence we need to manually link one by one. like FS if we have an option to choose whatever a relation type to be considered as default by the program, we can complete the task simply. In my housing project we have 80 roads with 9 different utilities where we have to give such relations on a go.
Member for
9 years 3 monthsI also tried to find this
I also tried to find this technique. But i came to the conclusion that their is no such way to get SS as default relationship.
Member for
16 years 3 monthsbigger question is why ?
bigger question is why ?
Member for
21 yearsno
no