Crashing the project Schedule

Member for

16 years 3 months

Fast Tracking VS Crashing the Schedule

 

Fast Tracking the schedule means to Revise the logic and do thing concurrently or in parallel which means that your manpower peak will be higher but it will be the same number of man-hours except for additional supervision.

A good rule of thumb is that sequential activities can sometimes be fast-tracked by up to 33%. In other words, if you're fast-tracking, you can start the second of two sequential activities when the first activity is 66% complete. So when you are 66% complete with the first conduit activity you can start the wire pulling.

 

Crashing the schedule means to reduce your durations but you will have to increase your man-hours because you need more men to do it in a shorter amount of time. You would shorten the duration of the activities on the critical path by throwing additional resources to the critical path without necessarily getting the highest level of efficiency. You might have to do several iterations because you crash one critical path then something else becomes critical. You will have increased cost in with this option

Member for

19 years 1 month

Not sure about this post. This was dated 2013, but why this shows on top? Anyhow, it's very interesting.

Given data (Original post), may not be complete (i.e. dependencies of the pipe sections if any in terms of location etc.). Anyway, if it was a constrained situation due to access issue, even if you put more resources to first section and finished earlier than scheduled, you will still get a Lag until you are allowed to start the second section. 

So what do you want? Make a claim for the standby time of your resources? Well, if I were the client, I would say that I notified you about the access issue just in time and I did not advise you to put more resources to the first section to finish early and make your resources standby until you'll be able to start the second section.

Well, if you can expound more, then perhaps you can establish a case. However, don't expect that a software can easily make a case for you. 

Member for

12 years 8 months

Hi..

Your case of Project Crash can be proved if you have finite resource for that activity or specific skills for that operation. generally, if you have common resource pool, primavera will not show the benefits as you expected. Hope you are convinced now!!