I would like to ask if its possible to back up the lack of coordiantes of right of way, by making refference to some external document may be there are standards of preparation woking darwings?
NB: there are no referrence to link between rigth of way and preparation of working drawings in the GCC & PCC of the project.
Then in my opinion you have a strong case for an EoT on the basis of late instruction / information provided you asked for the information in good time.
Member for
10 years 5 monthsOk, I'll search for
Ok, I'll search for that.
Thank you again.
Member for
19 years 10 monthsHi AbdulrahmanThat is beyond
Hi Abdulrahman
That is beyond my remit.
You will need to seek professional advice.
Best regards
Mike T.
Member for
10 years 5 monthsMany thanks Mike, I would
Many thanks Mike,
I would like to ask if its possible to back up the lack of coordiantes of right of way, by making refference to some external document may be there are standards of preparation woking darwings?
NB: there are no referrence to link between rigth of way and preparation of working drawings in the GCC & PCC of the project.
Member for
19 years 10 monthsHi AbdulrahmanThen in my
Hi Abdulrahman
Then in my opinion you have a strong case for an EoT on the basis of late instruction / information provided you asked for the information in good time.
Best regards
Mike Testro
Member for
10 years 5 monthsHi Mike,Thanks for replyThe
Hi Mike,
Thanks for reply
The client is responsuible to provide coordinates of right of way, from local state authorities.
At the date of preparation of working drawings, we had been provided with centerline of the road and benchmarks.
Member for
19 years 10 monthsHi AbdulrahmanThe key
Hi Abdulrahman
The key question is who was resposible for securing the right of way.
This is a common problem with linear projects such as roads and pipelines crossing land that has ownership disputes or common rights.
Best regards
Mike Testro