BL Duration % Complete

Member for

16 years 3 months

all of this is simply a math function of time

Scheduled duration % complete 

start date = 1/1/2017

contractual time 1025 calendar days

finish date = start date plus contractual time

1/1/2017 + 1025 days = 10/23/2019 finish date 

lets says the data date = 7/1/2018

days expended todate is data date - start date = 7/1/2018 - 1/1/2017 =  day # 546

scheduled duration % complete = current data datae (or day number) divided by over all duration which is 546/1025 = 53.27% 

 

actual duration % complete 

from your updated schedule the new forecasted completion date = 11/23/2019 

new time or new overall extened time is forecasted completion date minus the start date 11/23/2019-1/1/2017 = 1056 days

Actual duration % complete = current data dtae (or day number) divided by updated forecasted over all duration which is 546/1056 = 51.70%

this means that you are behind scedule 
Scheduled duration % complete = 53.27 % minus Actual Duration % complete    = 51.70%
 
Schedued VS Actual Progress  = 1.56% behind schedule
 
this can easily be done in a spread sheet 
 
its a strict math function as you can see

Member for

7 years 6 months

Thanks for the reply. I know that, normally I use schedule % to represent the progress but this time client is asking for suration %. Any help?

Member for

21 years 8 months

Float, the difference between Early and Late Dates is at the core of CPM scheduling. Baseline Schedule activities as well as any CPM Schedule activities do have Early Start/Finish Dates as well as Late Start/Finish Dates.  I suggest showing Current Schedule as well Baseline Schedules Early and Late Bars.

Baseline_Early_and_Late_Bars

  • The green/red bar represents Current Schedule Early Bar.
  • The white box represents Current Schedule Late Bar.
  • The yellow bar represents Baseline Early Bar.
  • The grey bar represents Baseline Late Bar.

Once you setup your schedule to display Baseline Late and Early bars you will not need to create any progress updates of your baseline, easy and gives you more information.

Using only Early Dates to compare planned % complete is wrong unless all activities are critical.