interface and Access dates for Rail sector

Member for

16 years 3 months

create milestones as handoff dates priior to your work starting. Make these constraint dates and get the dates from the responsible party.

So the completion of their activity is the predecessor to your work. Even if you only get a pdf file from  them create a activity in your schedule as a milestone and use their activity number in YOUR schedule. This way if you only get a pdf schedule update you know what activity number to look for