1st make sure that you are using the same calendars. Expecially if you are both using the default calendar.
2nd ask him to look at his schedule options f9 then options and see what he is using at the bottom of the general tab where it says Calendar for scheduling Relationship lag and make sure that they match
Member for
7 years 4 months
Member for7 years4 months
Submitted by Suhaib Nassar on Tue, 2018-07-03 10:59
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
7 years 4 monthsThank you Mr. Zoltan
Thank you Mr. Zoltan
Member for
16 years 3 monthswhen you same SAME calendar
when you same SAME calendar are they both using the default calendar if so then this is your problem they are different.
Member for
7 years 4 monthsDear Zoltan, I tried to
Dear Zoltan,
I tried to choose each option under Calender for Scheduling Relationship Lag, yeah the dates were changing but not exactly as per his file.
I have made sure before that we both are using the same calender. Any other ideas?
Member for
7 years 4 monthsDear Zoltan, I tried to
Dear Zoltan,
I tried to choose each option under Calender for Scheduling Relationship Lag, yeah the dates were changing but not exactly as per his file.
I have made sure before that we both are using the same calender. Any other ideas?
Member for
16 years 3 months1st make sure that you are
1st make sure that you are using the same calendars. Expecially if you are both using the default calendar.
2nd ask him to look at his schedule options f9 then options and see what he is using at the bottom of the general tab where it says Calendar for scheduling Relationship lag and make sure that they match
Member for
7 years 4 monthsDear Santosh, I also have
Dear Santosh,
I also have added BL Project Start & BL Project Finish columns, it also has the same finish date of BL1 which is in Septemper.
Dear Kirill,
Yes, I am sure he is using the same schedule
GUYS, I just found something cuz he just sent me his file
For example, the Finish date of activity (A) in 1-Oct-2017 with finish to start and (5) days lag with activity (B), and day 6-Oct-2017 is the holiday.
in my file, the Start date of (B) will be in 7-Oct-2017, whereas the Start Date of (B) in his file is in 5-Oct-2017
I think that there is one uncounted day in my lags, how can I maintain that?
Regards
Member for
20 years 6 monthsBL1 is what is referred to as
BL1 is what is referred to as the Primary Baseline, not the PROJECT Baseline. Make sure you have the right baselines referenced.
Member for
9 years 7 monthsDoes your client really has
Does your client really has BL1 at his schedule? Maybe he doesn't and you see some early planned finish