Hi Anel, 

The best representation for what your trying to acheive is via a Cashflow S-Curve. Example below. (Budget vs Actual vs Forecast to Completion)

In your case the Target / Forecast to Completion cummulative value will be less than the Original budget. 

I normally export data from P6 to excel to do the analysis and display charts. 

[[wysiwyg_imageupload:5694:]]

 

Hope this helps!!!

Member for

19 years 10 months

Hi Anel

The way you will save money is by reducing the programme duration and thereby the site overheads.

You can allocate a site cost per day on the overall summary bar and fix it as the baseline ost.

Adjustments to the original programme will either increase or decrease the sumary bar cost which can be compared by two columns in the table.

Trying to reduce costs on each individual task bar will not work.