Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2018-05-16 15:38 Permalink there are several thing that there are several thing that you can do 1. Clean the POBS tables in the existing database here is how Click on start All Programs, Microsoft SQl Server 2005, SLQ Server Management Studio Authentication: Should be SQL Server Authentication Login: sa Password: Prima123Vera Then click connect Expand the database folder and click on pmdb$primavera Then up top select new query Then type this delete POBS; the right click and select execute now you can close and exit out of sql 2. download this POBS cleaner adn clean every XER file prior to imporing it http://scheduleanalyzer.com/PurgePOBS.exe 3. You can exort the old projects as xer files save them to a thumb drive, an external hard drive or a network drive then delete these old projects. 4. You can create another database and stsrt to add NEW projects to that database Member for 21 years Member for 21 years Submitted by David Kelly on Tue, 2018-05-15 23:20 Permalink SQLite Management Studio. SQLite Management Studio. Don't leave home without it. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2018-05-16 15:38 Permalink there are several thing that there are several thing that you can do 1. Clean the POBS tables in the existing database here is how Click on start All Programs, Microsoft SQl Server 2005, SLQ Server Management Studio Authentication: Should be SQL Server Authentication Login: sa Password: Prima123Vera Then click connect Expand the database folder and click on pmdb$primavera Then up top select new query Then type this delete POBS; the right click and select execute now you can close and exit out of sql 2. download this POBS cleaner adn clean every XER file prior to imporing it http://scheduleanalyzer.com/PurgePOBS.exe 3. You can exort the old projects as xer files save them to a thumb drive, an external hard drive or a network drive then delete these old projects. 4. You can create another database and stsrt to add NEW projects to that database
Member for 21 years Member for 21 years Submitted by David Kelly on Tue, 2018-05-15 23:20 Permalink SQLite Management Studio. SQLite Management Studio. Don't leave home without it.
Member for
16 years 3 monthsthere are several thing that
there are several thing that you can do
1. Clean the POBS tables in the existing database here is how
Click on start All Programs, Microsoft SQl Server 2005, SLQ Server Management Studio
Authentication: Should be SQL Server Authentication
Login: sa
Password: Prima123Vera
Then click connect
Expand the database folder and click on pmdb$primavera
Then up top select new query
Then type this
delete POBS;
the right click and select execute
now you can close and exit out of sql
2. download this POBS cleaner adn clean every XER file prior to imporing it
http://scheduleanalyzer.com/PurgePOBS.exe
3. You can exort the old projects as xer files save them to a thumb drive, an external hard drive or a network drive then delete these old projects.
4. You can create another database and stsrt to add NEW projects to that database
Member for
21 yearsSQLite Management Studio.
SQLite Management Studio. Don't leave home without it.