Microsoft Project Updating - 2 Weeks Only

Member for

14 years 5 months

Hi Shane,

One way to do that is to set a baseline of your project and create a filter:

Field Name: "Baseline Finish"

Test: "is less than or equal to"

Value: input the date two weeks ahead from your status date (i.e., if the date today is 2 May '18, then input "16 May '18")

That will show you all the activities that should be completed before and on 16 May '18.

 

Hope this helps.

Regards,

PH