-my duration type is fixed duration & units.. i follow in that way
-actual units or cost that subtract actual from at completion is checked
-recalculate actual units and cost when duration % complete changes is unchecked because my activity % completion type is physical . i enter actual units or cost manually with real numbers
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Mon, 2018-04-16 13:44
make sure that the duration type is set to fixed duration and units/time
also go to PROJECTS and make sure that you project is highlighted and on the calculations tab make sure that under Resource assignments that When updating actual units or cost that subtract actual from at completion is checked and that recalculate actual units and cost when duration % complete changes.
Member for
16 years 3 months1. open the project and
1. open the project and select send project and email it to yourself before you do any changes. Its like making a back up if things go haywire.
2. next make sure that the duration type is fixed duration / units per time yours is not add the column for duration type and do a fill down
3. make sure that your activites are task not resource dependent
4. do a global change
where calcuate costs fron units equal yes
then
calcuate costs from units = no
then select change on the right and then comitt changes
Member for
16 years 5 monthsZoltan,-my duration type is
Zoltan,
-my duration type is fixed duration & units.. i follow in that way
-actual units or cost that subtract actual from at completion is checked
-recalculate actual units and cost when duration % complete changes is unchecked because my activity % completion type is physical . i enter actual units or cost manually with real numbers
Member for
16 years 3 monthsmake sure that the duration
make sure that the duration type is set to fixed duration and units/time
also go to PROJECTS and make sure that you project is highlighted and on the calculations tab make sure that under Resource assignments that When updating actual units or cost that subtract actual from at completion is checked and that recalculate actual units and cost when duration % complete changes.