Weekly S curve for progress

Member for

13 years 9 months

And don't forget the new "EVA Reporter" export tool, which has superseded the older Progress Expert macro and is now included in all versions from 14 onwards...

Member for

19 years 10 months

Hi Paul

Can be cost but the better measure is resource hours or even labour costs. days progress.

Another is planned days progress over actual 

Expenditure of cost is not a true reflection of progress.

I call this the Golden Tap Syndrome - A gold tap costs 100 time a chrome one and takes the same time to fit.

Best regards

Mike T.

Member for

8 years 4 months

Thanks mike, is this done through the resource graphs set as cost centres?

Member for

19 years 10 months

Hi Paul

You can set up any histgrams comparing planned with actual with a multiple set of data.

The graphs though are better presented on a spreadsheet when the data is exported.

Best regards

Mike Testro