Delay Analysis

Member for

15 years 10 months

Hi 

How to deal with the following situation,

 

Contractor completed all the works other than the suspended works , which has to be executed upon completion of main works. 

the suspended works were released to contractor after few weeks , 

how this situation is to deal to establish the extension of time claim 

 

Regards 

Bilal

Member for

19 years 10 months

Hi Shahin

A new topic should be under its own heading - not piggy back on an existing topic.

Please start again under a new heading and i will answer your query.

Best regards

Mike testro - Moderator

Member for

7 years 6 months

hi everyone

I'm confused about differences between "Contemporaneous Time Impact Analysis" and "Forensic Time Impact Analysis". can anyone explain me what are the differences between these two topic?

Member for

17 years 4 months

Hi Ibah,

Client may wants to see the concurrent delay from your side, related to prolongation cost.

So the data date of the programme should be the date on which the road was planned to handed over to you in the revised baseline programme. 

It will show whether all other available areas which were supposed to finish with in the previous granted EOT of 6 months is finishing on time or not.

Best Regards

Kannan

Member for

19 years 10 months

Hi Ihab

It doesn't realy matter what forecat date you use in an impacted analysi for future works.

Your actual entitlement will be fixed on the  actual date.

With this length of delay you should be looking at your contract with a view to re rating your fixed price elements.

Or even termination if that suits better.

Best regards

Mike Testro