Setting a start date

Member for

8 years 4 months

while a constraint would work, i would suggest adding an activity with the necessary logic for the 2 week lag such as "gas utility availabe to peform hook-up' 

Member for

7 years 9 months

Thansk Mike :) Worked a treat, just what I was after!

Member for

7 years 9 months

Thansk Mike :) Worked a treat, just what I was after!

Member for

19 years 10 months

Hi James Welcome to Planning Plant

The easiest way is to put a "Must Start On or After" constraint flag on the task.

Be careful of these because Powerproject does not work on negative float.

Best regards

Mike T.