Copying Custom Calendar between projects

Member for

7 years 9 months

Thanks Mike.  I did try the copy and paste but maybe I wasn't doing it correctly.  I was able to copy a task, and paste it into the new schedule and it carried the calendar with it.

Thanks again!

Jeff

Member for

19 years 10 months

Hi Jeff

Highlight and copy the calendar you want.

Go to the new project and copy the calendar.

If the calendar wizard pops up then disable it first.

Alternatively copy a single task and copy it into the new projoject and it should bring all the other objects with it for you to retain or de select.

Best regards

Mike T.