Weight Factor

Member for

22 years 3 months

ِDear Testro

Hi,

you are right, but my method is a simple sample for buttom up approach. the best solution depend on Create S.W.U for Project.

 

B/R

Member for

19 years 10 months

Cost is not a reliable method of reporting progress.

Your split of 70 / 30 is too broad an average when in some task the split is 20 / 80 and others 90 / 10.

If you are going to apply this method then you must allocate the correct split to each task.

Also there is a 3rd split of OH&P which is not progress related at all.

Member for

22 years 3 months

Dear moutaz

Hi,

the best way for create weight factors as following items:

1- Cost ( 70 % share)

2- Time ( 30 % share)

Total weight= 70% w.cost+ 30% w.Time

Also you need determain the S.W.U ( Specific Work Units) for in the WBS units.

 

Best Regards

Rashidi

Member for

21 years 10 months

Jithin

the case i have is not construction and both time and cost are preferable to be used, my question is how to use both?

best,

muataz

Member for

19 years 10 months

Hi Moutaz

Weightage only becomes a problem when a planned task s a combination of trades and/or location ie:

FRC Suspended slabs : 20-10-17 > 15-12-17 > 40d

When this task is spread over - say - 5 slabs then you have both a time and cost weithage problem.

This is because planners are lazy and lack pride in their profession.

It is just as easy to plan the work in detail ie:

Level 1

Slab Form > Rebar > Edge Forms > Pour Concrete

Level 2

                Slab Form > Rebar > Edge Forms > Pour Concrete

Etc

Then you just report % complete in either time or volume on each task.

Best regards

Mike T.

Member for

14 years 7 months

Hi Moutaz,

To Calulate weightage you can do it by either

  • By Only Cost
  • By Time and Cost

If the Project is only Construction then Manhours / Activity would be good.

If the Project is Engineering, Procurement and Construction then it would be better to use Manhours / Deliverable, Cost / Item and Manhours / Activity to measure each WBS.

 

In an Overall summary ou can use Cost or the weightage given by Client.

 

Regards

Jithin