Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2017-10-03 15:17 Permalink 2 things to check 1. make 2 things to check 1. make sure that the duration TYPE is set to fixed duration & units/time you might have to add the column for duration type change the 1st one to fixed duration & units/time then do a fill down for that column. 2. go to the project directory make sure that your porject is highlighted click on calculations then in the lower left make sure that reset remaining duration and units to original Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2017-10-03 15:17 Permalink 2 things to check 1. make 2 things to check 1. make sure that the duration TYPE is set to fixed duration & units/time you might have to add the column for duration type change the 1st one to fixed duration & units/time then do a fill down for that column. 2. go to the project directory make sure that your porject is highlighted click on calculations then in the lower left make sure that reset remaining duration and units to original
Member for
16 years 3 months2 things to check 1. make
2 things to check
1. make sure that the duration TYPE is set to fixed duration & units/time
you might have to add the column for duration type change the 1st one to fixed duration & units/time then do a fill down for that column.
2. go to the project directory make sure that your porject is highlighted click on calculations then in the lower left make sure that
reset remaining duration and units to original