keeping external links

Member for

19 years 1 month

Normally I'd agree but I just cannot understand why it does on one and not on another.  The second one the supplier updates the project number each month following an update yet my links stay the same.  The other is the same supplier and does the same but it loses them and has to be re-established each month.

 

I wondered if there were a setting that stops it being lost or whether setting a status on the project would do it as one is active and one inactive.

 

Member for

16 years 3 months

Thats very strange if the project number is changed ANY link would be lost