Why 331d is still a mystery. It is a 3 to 1 ratio depending on time of day for start and finish dates. It might be the issue is within work patterns, perhaps an 8 h/d work pattern assigned to a 24 h/d calendar (?). I do not use Asta PP but look for knowledge everywhere. Work patterns is an interesting concept.
Work patterns on the same calendar are perhaps unique to Asta Power Project. Work patterns look like applying multiple work weeks to different periods on same calendar, a special kind of calendar exception. This can be a common situation in some industries like Hospitals and Airlines.
Its use can be transparent if when displaying calendar on calendar column you can also display work patterns: Calendar1(WP1,WP2,…).
Two thumbs up to Asta Power Project.
Availability of resources is not only defined by work hours but might also be by geographical location. I wonder how location patterns could be better implemented.
Again the float errors are only for the Actvities assigned to a 7 day calendar .........while the correct float is indicated on screen but i get a different float when i run a report
Member for
21 years 8 monthsStart Float cannot be greater
Why 331d is still a mystery. It is a 3 to 1 ratio depending on time of day for start and finish dates. It might be the issue is within work patterns, perhaps an 8 h/d work pattern assigned to a 24 h/d calendar (?). I do not use Asta PP but look for knowledge everywhere. Work patterns is an interesting concept.
Working with Asta PP Work Patterns
Work patterns on the same calendar are perhaps unique to Asta Power Project. Work patterns look like applying multiple work weeks to different periods on same calendar, a special kind of calendar exception. This can be a common situation in some industries like Hospitals and Airlines.
Its use can be transparent if when displaying calendar on calendar column you can also display work patterns: Calendar1(WP1,WP2,…).
Two thumbs up to Asta Power Project.
Availability of resources is not only defined by work hours but might also be by geographical location. I wonder how location patterns could be better implemented.
Member for
19 years 10 monthsHi DanielHow are you running
Hi Daniel
How are you running your report?
Best regards
Mike T.
Member for
8 years 4 monthsAgain the float errors are
Again the float errors are only for the Actvities assigned to a 7 day calendar .........while the correct float is indicated on screen but i get a different float when i run a report
Member for
13 years 8 monthsdeleted
deleted
Member for
19 years 10 monthsEmadThis is an Asta forum not
Emad
This is an Asta forum not P6.
Daniel
Float is always displayed in working days.
You may be comparing the result with calendar (ed) days.
Best regards
Mike T.