But Bar no 11 is still on shaded timescale where the part of that bar showing in orange/red highlighted in screenshot-http://ge.tt/2aq3Kol2) coming on shaded holidays timescale, must start after holidays
My question is that what steps I need to follow so Orange/red part showing on shaded timescale must start after holidays timescale automatically?
Member for
9 yearsThanks Mike
Thanks Mike
Member for
19 years 10 monthsHi Andy - sorry for the late
Hi Andy - sorry for the late response but I had some deadlines to meet.
What you have shown is the task bar sitting over the holiday period which is the normal view.
The tasks start and end over the holiday period but the working days will remain the same duration - this is completely normal.
You can set the view so that the holiday shading sits over the bar using >Format > Barchart > Non Working - and select required display.
Or you block out the holiday completely in the same dialogue.
Best regards
Mike T.
Member for
9 yearsMike may be busy.Some other
Mike may be busy.
Some other expert asta user also in this forum being asta is leading softwrare. Asta support people also visiting the forum.
No one have answer of it.. Strange ????
Can someone solve this issue please?
cheers,
Andy
Member for
9 yearsSorry MikeCheck now
Sorry Mike
Check now please
http://imgur.com/a/m0e4J
Need to move part of bar 11 ans 12 showing on shaded timescale .
Thanks,
Member for
19 years 10 monthsHi AndyCan't open it.You need
Hi Andy
Can't open it.
You need to work out how to put an image on PP.
Rafael Davila is an expert.
Best regards
Mike T.
Member for
9 yearsbar.pngHi Mike Here is the
[[wysiwyg_imageupload:4882:]]Hi Mike
Here is the image
Regards,
Andy
Member for
19 years 10 monthsHi AndyLink does not workBest
Hi Andy
Link does not work
Best regards
Mike Testro
Member for
9 yearsHi Mike,Thanks for replying.
Hi Mike,
Thanks for replying.
Necking problem has been solved.
But Bar no 11 is still on shaded timescale where the part of that bar showing in orange/red highlighted in screenshot- http://ge.tt/2aq3Kol2) coming on shaded holidays timescale, must start after holidays
My question is that what steps I need to follow so Orange/red part showing on shaded timescale must start after holidays timescale automatically?
Regards,
Andy
Member for
19 years 10 monthsHi AndyYou are displaying the
Hi Andy
You are displaying the P6 replica view with necking.
The stanard powerproject view is a simple straight bar - just disable the necking facility.
To simply hide a bar from view then Right click on task > Properties > select for hiding> In the format ribon click the Hide icon.
Best regards
Mike Testro