Hi, at what stage are you in the project is it running efficient and delayed or is it delayed and not running efficient. If I can know this I will be able to help.
The delay is the difference between the current projected programme completion date and the contract completion date. It will remain an estimate until you have completed the work.
There is no standard report form but it is essential that you follow your contract rules when sending a notice of any delay. And make sure you do it in time.
Member for
11 years 10 monthsHi Mikein P6 i can see the
Hi Mike
in P6 i can see the expected finish date on every update
but, how can i see it in Asta?
Member for
16 years 9 monthsHi, at what stage are you in
Hi, at what stage are you in the project is it running efficient and delayed or is it delayed and not running efficient. If I can know this I will be able to help.
Member for
19 years 10 monthsHi DominicThe delay is the
Hi Dominic
The delay is the difference between the current projected programme completion date and the contract completion date. It will remain an estimate until you have completed the work.
There is no standard report form but it is essential that you follow your contract rules when sending a notice of any delay. And make sure you do it in time.
Best regards
Mike T.