Total Manpower

Member for

24 years 9 months

As was discussed before resource hours and resource quantities are not proportional.

But in any case the number of workers is not the same during the project life cycle. The number of workers at any time is determined by the project schedule.

Member for

16 years 3 months

if you have the estimated manhours then you should know out of the 175,000 manhours how much is direct and indirect how did you come uo with this numebr in the first place ?