Thanks a lot Tom, however I would like to comment that in P6, once you schedule you get a report including the open end tasks.

Best,

Muataz

Member for

19 years 10 months

Alternatively just look for large amounts of float.

Member for

18 years 11 months

Make a new filter called "Open Ends" with the following criteria:

- Predecessors - equals - [empty field]

Or - Successors - equals - [empty field]

For "[empty field]," enter no characters at all.

Then include this filter in your report specification - or just apply the filter in a view.

 

Note: this is the simplest "open-ends" criteria, same as P6, and does not include dangling starts/finishes.  Filtering danglers requires a little macro code ("vba").