Leveling for effort is not the same as leveling for resource quantity and can yield unfeasible results.
The need for separate fields for resource quantity and effort is not just a matter of convenience it is also a matter of getting reliable resource overload visibility and resource leveling.
Member for
21 years 8 monthsPlease be reminded
Please be reminded that:
The need for separate fields for resource quantity and effort is not just a matter of convenience it is also a matter of getting reliable resource overload visibility and resource leveling.
Member for
16 years 1 monthThanks, I'll try it
Thanks, I'll try it
Member for
21 years 8 monthsI do not use MSP but always
I do not use MSP but always look to understand the basics of it. Try the following.