Bem eu gosto e costumo usar com frequencia a Analise probabilistica com Monte Carlo no Spider Project, resalto que ate em sua versão de treinamento pode-se usar apenas respeitando a limitação de 200 atividades produtivas dentro do programa na versao de treinamento.
Fiz o treinamento do Marcus Possi e foi de grande proveito em meus projetos
espero ter ajudado
Member for
1 year 5 months
Member for1 year5 months
Submitted by lb*****@g***** on Sat, 2024-07-13 14:52
But remember that external software shall not be used for MC analysis of resource-constrained schedules. And most external programs do not even try to model resource-constrained schedules.
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Fri, 2017-02-24 11:48
Member for
4 yearsBem eu gosto e costumo usar
Bem eu gosto e costumo usar com frequencia a Analise probabilistica com Monte Carlo no Spider Project, resalto que ate em sua versão de treinamento pode-se usar apenas respeitando a limitação de 200 atividades produtivas dentro do programa na versao de treinamento.
Fiz o treinamento do Marcus Possi e foi de grande proveito em meus projetos
espero ter ajudado
Member for
1 year 5 monthsHello David, 1. Oracle
Hello David,
1. Oracle Primavera Risk Analysis (formerly Pertmaster)
2. @Risk by Palisade
3. RiskAMP
4. Safran Risk
5. Spider Project
Thanks,
Member for
13 years 11 monthsI sceond David's suggestion
I sceond David's suggestion of Full Monte barbecana.com and I heard that Primavera Risk Analysis was being depreciated.
Member for
24 years 8 monthsBut remember that external
But remember that external software shall not be used for MC analysis of resource-constrained schedules. And most external programs do not even try to model resource-constrained schedules.
Member for
22 years 9 monthsHi David,Maybe it's too late,
Hi David,
Maybe it's too late, much too late ?
Have a look at Full Monte (http:barbecana.com) and RiskProject (Intaver.com); both can work stand-alone, with P6 or MSP
Regards,
Alexandre