The Hammock type activity will work if task 1 and 3 are both milestones. Add them to a hammock activity called Guard delivered building material

Member for

19 years 10 months

Hi Ben

A buffer task is infinitely flexible between the movement of the start and finish links depending on both upstream and downstream movement.

What more do you want?

Best regards

Mike T.

Member for

9 years 2 months

Hi Mike,

 

Making it into a buffer task will only affect the start of the buffer task depending on the movement of its predeccesor, the back end of the buffer task will have a deadline constraint applied to it. What if i want the completion of a seperate task to drive the completion of a the buffer task (with a FF link)?

So i will have two task with a gap between them. The tasks may fluctuate in terms of start/completion dates, but a seperate task linked in between them will automatically fluctuate in duration along with them, to replace the gap between the two task. 

Member for

19 years 10 months

Hi Ben

Use a BUFFER task.

Creat a normal task using FS links and then Make Into> Buffer.

This is unique to Asta and does precisely what you wish.

There is an option to make it critical or not.

Best regards

Mike Testro

Member for

9 years 5 months

Hi Ben,

I would have thought Asta has "Level of Effort" type tasks......?