I have another problem, is there any simple way of adding activities in P3e as like pressing "down arrow" key button in P3, in P3e every time i’ve to use "Insert" key button to add a new activity.
Regards
Daya
Member for
20 years 7 months
Member for20 years8 months
Submitted by Niek Zonneveld on Thu, 2005-04-28 03:50
Can someone guide me step by step procedure of how to configure/establish a connection to a new database instead of PMDB(default) in P3e/c via interBase.
The reason PMDB contains default EPS and resources etc., Is there a way to create a fresh database when i use interBase connection.
We have just done a similar exercise - although with fewer users; you will need to do a number of things but it is possible to import your plans directly - if you do this there is an awful lot of clearing up however. The best way is to define standard parameters - calendars; resources etc; and do the clean up in P3 before transfer. You will need to think about reporting requirements - WBS etc for P3e prior to import and develop EPS/OBS accordingly - try to keep these as simple as possible for a start limit OBS to your planners for example.
Take it step by step ie One planners plan at a time.
Member for
23 years 8 months
Member for23 years8 months
Submitted by Dinesh Kumar D… on Mon, 2005-04-25 00:45
Suggest you check out the Knowlege database on the Primavera site. There may be issues if you are converting several project groups. You need to do some data cleansing on resources, codes and calendars. The thing to remember is that you are migrating data into a common database and it is easy to corrupt/duplicate data.
Member for
20 years 6 monthsRE: Migration from P3 (ver. 3.1) to P3e ?
Hey All:
How did this thread change from "migrating data from P3 to P3e" to "how to use P3e"?
Jayant
Member for
22 years 7 monthsRE: Migration from P3 (ver. 3.1) to P3e ?
Niek, Thanks for your suggestion.
I have another problem, is there any simple way of adding activities in P3e as like pressing "down arrow" key button in P3, in P3e every time i’ve to use "Insert" key button to add a new activity.
Regards
Daya
Member for
20 years 7 monthsRE: Migration from P3 (ver. 3.1) to P3e ?
The way to do that is renaming the current PMDB.GDB (if you to keep it) and replace it with a copy of the empty PMDB.GDB on the installation CD.
You only need to update your reference to the license key and then you can login with admin.
Hope this helps,
Niek.
Member for
22 years 7 monthsRE: Migration from P3 (ver. 3.1) to P3e ?
Can someone guide me step by step procedure of how to configure/establish a connection to a new database instead of PMDB(default) in P3e/c via interBase.
The reason PMDB contains default EPS and resources etc., Is there a way to create a fresh database when i use interBase connection.
Member for
20 years 9 monthsRE: Migration from P3 (ver. 3.1) to P3e ?
We have just done a similar exercise - although with fewer users; you will need to do a number of things but it is possible to import your plans directly - if you do this there is an awful lot of clearing up however. The best way is to define standard parameters - calendars; resources etc; and do the clean up in P3 before transfer. You will need to think about reporting requirements - WBS etc for P3e prior to import and develop EPS/OBS accordingly - try to keep these as simple as possible for a start limit OBS to your planners for example.
Take it step by step ie One planners plan at a time.
Member for
23 years 8 monthsRE: Migration from P3 (ver. 3.1) to P3e ?
Hi,
My opinion is the same as what Mr.Bill has.
Thanks & regards
Dinesh
Member for
23 years 11 monthsRE: Migration from P3 (ver. 3.1) to P3e ?
Suggest you check out the Knowlege database on the Primavera site. There may be issues if you are converting several project groups. You need to do some data cleansing on resources, codes and calendars. The thing to remember is that you are migrating data into a common database and it is easy to corrupt/duplicate data.
Proceed with caution.
Dave Forrest
Senior Consultant
ForgeTrack Ltd
a.k.a. President of Primavera UK User Group.