In the STO's execution phase you will face the additional works, So to incorporating these activities on the schedule you have to be sure that these activities will not affecting the late finish date of the shutdown, otherwise you can keep these works for the next shutdown.
But about how to be sure that these additional activities will not delay the project, you have to make a leveling resources in keeping the same priorities by area by systeme.
In the STO's execution phase you will face the additional works, So to incorporating these activities on the schedule you have to be sure that these activities will not affecting the late finish date of the shutdown, otherwise you can keep these works for the next shutdown.
But about how to be sure that these additional activities will not delay the project, you have to make a leveling resources in keeping the same priorities by area by systeme.
Member for
10 years 1 monthCiao, In the STO's
Ciao,
In the STO's execution phase you will face the additional works, So to incorporating these activities on the schedule you have to be sure that these activities will not affecting the late finish date of the shutdown, otherwise you can keep these works for the next shutdown.
But about how to be sure that these additional activities will not delay the project, you have to make a leveling resources in keeping the same priorities by area by systeme.
Regards,
K.SAADI
Member for
10 years 1 monthCiao, In the STO's
Ciao,
In the STO's execution phase you will face the additional works, So to incorporating these activities on the schedule you have to be sure that these activities will not affecting the late finish date of the shutdown, otherwise you can keep these works for the next shutdown.
But about how to be sure that these additional activities will not delay the project, you have to make a leveling resources in keeping the same priorities by area by systeme.
Regards,
K.SAADI
Member for
19 years 10 monthsHi FlorisIt is standard
Hi Floris
It is standard practice for extra work to be added to the programme as task bars.
They may affect the critical path.
Rescheduling should be done as often as is necessary.
Best regards
Mike Testro
Member for
11 years 3 monthsNobody ?
Nobody ?