There is an unbreakable link in Automatically Scheduled tasks. So if you change any of these parameters after you have initially created the Task, it will affect the others.
If you change the Task Type to: Manually Scheduled. Make the Required changes and then remember to change back to Automatically Scheduled, you should find that you were able to change just the field expected, without breaking anything else.
Member for
9 years 3 monthsHi Raf, There is an
Hi Raf,
There is an unbreakable link in Automatically Scheduled tasks. So if you change any of these parameters after you have initially created the Task, it will affect the others.
If you change the Task Type to: Manually Scheduled. Make the Required changes and then remember to change back to Automatically Scheduled, you should find that you were able to change just the field expected, without breaking anything else.
Did this solve your problem?
Kind regards,
Phil
Member for
9 years 3 monthsThanksOne more question;when
Thanks
One more question;
when I change the activity duration the manhrs assigned change automatically, how can I avoid this?
Member for
18 years 11 monthsRaf,Change the Task type from
Raf,
Change the Task type from Fixed Units (the default) to Fixed Duration.
Good luck, tom