Microsoft Project Member for 12 years 2 months Member for 12 years 2 months Submitted by ss.dhatwalia on Wed, 2016-08-17 13:34 Permalink I did it using the exceptions I did it using the exceptions tab made an exception called "Alternate Sunday" Then click - details; Non-Working radio button is selected & used the recurrence pattern. If any other method is there plz let me know. Log in or register to post comments
Member for 12 years 2 months Member for 12 years 2 months Submitted by ss.dhatwalia on Wed, 2016-08-17 13:34 Permalink I did it using the exceptions I did it using the exceptions tab made an exception called "Alternate Sunday" Then click - details; Non-Working radio button is selected & used the recurrence pattern. If any other method is there plz let me know.
Member for
12 years 2 monthsI did it using the exceptions
I did it using the exceptions tab
made an exception called "Alternate Sunday"
Then click - details; Non-Working radio button is selected &
used the recurrence pattern.
If any other method is there plz let me know.