Its the duty of respective Site Engineer to give you the progress who would be given progress by there supervisors on a daily basis. This should be passed on to you. But you would have to go to site and cross check if something is missing from the reported progress and it would be a good learning expeeirnce too.
Using the progress reports you are getiing from your Site Engineer (HVAC, Plumbing, Electrical) prepare a report. In your report during the Basline stage itself you need to know what is the quantity for example if its a Tower Floor wise and then measure the progress according to that.
Member for
14 years 7 monthsHi Anand,Its the duty of
Hi Anand,
Its the duty of respective Site Engineer to give you the progress who would be given progress by there supervisors on a daily basis. This should be passed on to you. But you would have to go to site and cross check if something is missing from the reported progress and it would be a good learning expeeirnce too.
Using the progress reports you are getiing from your Site Engineer (HVAC, Plumbing, Electrical) prepare a report. In your report during the Basline stage itself you need to know what is the quantity for example if its a Tower Floor wise and then measure the progress according to that.
Regards
Jithin