Project Management Issues Discussion Member for 10 years 1 month Member for 10 years 2 months Submitted by abbas2009 on Sun, 2015-09-27 07:37 Permalink Thank Mike. Thats exactly Thank Mike. Thats exactly what happened the consultant submitted his offer then we had a detailed discussion and negotiation unitl we agreed on the final fees. Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Wed, 2015-09-23 07:55 Permalink Hi Abbas - Welcome to Hi Abbas - Welcome to planning planet. You say the variations will affect the design massively which implies that a large part of the original design will have to be done again. There is no "correct" way to calculate the ammount to be paid. You can ask the designer to break down his fees so that you can check if it is reasonable. My advice is to negotiate a reasonable fixed fee rather than pay by the hour. Best regards Mike Testro Log in or register to post comments
Member for 10 years 1 month Member for 10 years 2 months Submitted by abbas2009 on Sun, 2015-09-27 07:37 Permalink Thank Mike. Thats exactly Thank Mike. Thats exactly what happened the consultant submitted his offer then we had a detailed discussion and negotiation unitl we agreed on the final fees.
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Wed, 2015-09-23 07:55 Permalink Hi Abbas - Welcome to Hi Abbas - Welcome to planning planet. You say the variations will affect the design massively which implies that a large part of the original design will have to be done again. There is no "correct" way to calculate the ammount to be paid. You can ask the designer to break down his fees so that you can check if it is reasonable. My advice is to negotiate a reasonable fixed fee rather than pay by the hour. Best regards Mike Testro
Member for
10 years 1 monthThank Mike. Thats exactly
Thank Mike.
Thats exactly what happened the consultant submitted his offer then we had a detailed discussion and negotiation unitl we agreed on the final fees.
Member for
19 years 10 monthsHi Abbas - Welcome to
Hi Abbas - Welcome to planning planet.
You say the variations will affect the design massively which implies that a large part of the original design will have to be done again.
There is no "correct" way to calculate the ammount to be paid.
You can ask the designer to break down his fees so that you can check if it is reasonable.
My advice is to negotiate a reasonable fixed fee rather than pay by the hour.
Best regards
Mike Testro